About 2 Months Into Closure Of Valley Forge Road Bridge, Frustrations Running High

By Jim Melwert

PHILADELPHIA (CBS) -- About two months into the closure of the Valley Forge Road bridge between Phoenixville and Valley Forge, and frustrations are running high. While some elected officials are pushing for a late-summer opening, PennDOT says it is doing all it can to get the busy roadway re-opened as soon as possible.

PennDOT says they've re-worked the contract to expedite the Route23-Valley Forge road bridge with a new end date of November 26th, and a $3,000 a day incentive for an early completion.

State Senator Andy Dinniman says the bridge closure is a hardship on residents and businesses in the area and he'll continue to push for an earlier opening.

"PennDOT is giving a November date, but PennDOT can complete this in September," said Dinniman.

But PennDOT spokesman Charles Metzger is hesitant to peg a specific date, but says the contractor is:

"He's working five ten-hour days now. He's brought on extra guys to help get construction rolling at a little bit of a quicker pace."

During the closure 19,000 cars per day are pushed onto small side streets or to the already jammed Route 422.

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.