High-Speed Rail Lawsuit Delays Cost $63M, 17 Months

SACRAMENTO (AP) — California high-speed rail officials are signing a $63 million contract extension that also extends the deadline by 17 months for finishing a 29-mile stretch of rail line in the Central Valley.

It comes after landowners who sought to block the project there lost a nearly five-year legal fight that sought to block the project.

They sued to stop financing of the $64 billion project, but a Sacramento County Superior Court judge ruled against them in March.

On Tuesday, rail officials said they signed a new contract with construction vendor Tutor Perini/Zachry/Parsons.

High-speed rail spokeswoman Lisa Marie Alley says the higher cost was built into a $160 million reserve included in the original budget and will not affect the project's overall budget and schedule.

(Copyright 2016 The Associated Press. All rights reserved. This material may not be published, broadcast, rewritten or redistributed.)

Read more
f

We and our partners use cookies to understand how you use our site, improve your experience and serve you personalized content and advertising. Read about how we use cookies in our cookie policy and how you can control them by clicking Manage Settings. By continuing to use this site, you accept these cookies.