Glitches Nag New Air Traffic Control Computers
(AP)
New computers crucial to modernizing the U.S. air traffic control system have run into serious problems and may not be fully operational by the end of this year when the current system is supposed to be replaced, a government watchdog said Wednesday.
The $2.1 billion computer system has misidentified aircraft and had trouble processing radar information, Calvin Scovel, the Transportation Department's inspector general, told a House panel. Air traffic controllers at a Federal Aviation Administration radar center in Salt Lake City, where the new computers are being tested, also have had difficulty transferring responsibility for planes to other controllers, he said.
Scovel warned that if the problems continue they could delay the FAA's NextGen program to replace the current air traffic control system, which is based on World War II-era radar technology, with a new system that's based on GPS technology.
The troubled computer system, called En Route Automation Modernization, is designed to handle aircraft flying at higher altitudes between airports, rather than planes taking off or landing. While not specifically part of the NextGen program, it is a critical underpinning.
The FAA had planned to have ERAM operational in Salt Lake City by December 2009 and at the agency's 20 other radar centers that handle en route traffic by the end of this year. That's when the FAA's contract with IBM to maintain the present computer system expires. The present system relies on a unique computer language called Jovial that is understood by a dwindling number of technicians.
FAA Spending $14 million a month
However, deployment of the system in Salt Lake City has been delayed six months, and it is unlikely that the FAA will be able to have ERAM fully working in the 20 other radar centers by the end of this year, the inspector general said. The FAA is spending $14 million a month trying to resolve the problems and get the system working, Scovel told the House Transportation and Infrastructure aviation subcommittee.
"FAA officials are concerned about the ERAM transition at larger, more complex (radar centers) like Chicago and New York," he said. Those centers have unique air traffic control demands that will require adaptations to the ERAM software, Scovel said.
FAA spokeswoman Laura Brown said the agency is working to resolve the problems at the Salt Lake City center.
"We want to make sure the system is operating smoothly before we expand ERAM to other sites," Brown said. "We do not expect the minor delays in ERAM to slow down the transition to NextGen."
Scovel also said problems with a new FAA telecommunications systems raise questions about whether it can be relied upon for NextGen.
A failure of the system in November delayed more than 800 flights nationwide, and it took the FAA and its contractor over five hours to restore service, he said. The FAA has established review teams to assess the overall system design, he said.
Another witness at the hearing complained that a federal environmental law could delay the start of a key portion of NextGen even though the new air traffic system is projected to significantly save fuel and reduce greenhouse gas emissions by allowing planes to fly faster, more direct routes.
Changing flight path designs will require environmental impact statements that could take years to complete and add millions of dollars to the cost of NextGen, said Lorraine Bolsinger, president and CEO of General Electric Aviation Systems, a key contractor.
The $2.1 billion computer system has misidentified aircraft and had trouble processing radar information, Calvin Scovel, the Transportation Department's inspector general, told a House panel. Air traffic controllers at a Federal Aviation Administration radar center in Salt Lake City, where the new computers are being tested, also have had difficulty transferring responsibility for planes to other controllers, he said.
Scovel warned that if the problems continue they could delay the FAA's NextGen program to replace the current air traffic control system, which is based on World War II-era radar technology, with a new system that's based on GPS technology.
The troubled computer system, called En Route Automation Modernization, is designed to handle aircraft flying at higher altitudes between airports, rather than planes taking off or landing. While not specifically part of the NextGen program, it is a critical underpinning.
The FAA had planned to have ERAM operational in Salt Lake City by December 2009 and at the agency's 20 other radar centers that handle en route traffic by the end of this year. That's when the FAA's contract with IBM to maintain the present computer system expires. The present system relies on a unique computer language called Jovial that is understood by a dwindling number of technicians.
FAA Spending $14 million a month
However, deployment of the system in Salt Lake City has been delayed six months, and it is unlikely that the FAA will be able to have ERAM fully working in the 20 other radar centers by the end of this year, the inspector general said. The FAA is spending $14 million a month trying to resolve the problems and get the system working, Scovel told the House Transportation and Infrastructure aviation subcommittee.
"FAA officials are concerned about the ERAM transition at larger, more complex (radar centers) like Chicago and New York," he said. Those centers have unique air traffic control demands that will require adaptations to the ERAM software, Scovel said.
FAA spokeswoman Laura Brown said the agency is working to resolve the problems at the Salt Lake City center.
"We want to make sure the system is operating smoothly before we expand ERAM to other sites," Brown said. "We do not expect the minor delays in ERAM to slow down the transition to NextGen."
Scovel also said problems with a new FAA telecommunications systems raise questions about whether it can be relied upon for NextGen.
A failure of the system in November delayed more than 800 flights nationwide, and it took the FAA and its contractor over five hours to restore service, he said. The FAA has established review teams to assess the overall system design, he said.
Another witness at the hearing complained that a federal environmental law could delay the start of a key portion of NextGen even though the new air traffic system is projected to significantly save fuel and reduce greenhouse gas emissions by allowing planes to fly faster, more direct routes.
Changing flight path designs will require environmental impact statements that could take years to complete and add millions of dollars to the cost of NextGen, said Lorraine Bolsinger, president and CEO of General Electric Aviation Systems, a key contractor.
Popular Now in SciTech
- Angry Birds take off in "space"
- Simpsons Arcade finally makes it to Xbox 360, PS3
- Apple iPhone 5 rumors, reports say June release
- Apple MacBook Pro getting makeover, says new report
- Foxconn says it will raise salaries
- Facebook required for Spotify account, here's a trick
- Is Final Fantasy XIII-2 worth your time?
- Mountain Lion, Apple OS may drop support for older Macs
- How to get the Diablo III beta test
- Microsoft redesigns Windows logo
- PS Vita launch day titles and pricing details
- Apple iPad 3 rumors resurface, sources say March release
- Shocking Stats on Texting While Driving
- Apple closer to winning "iPad" name
- Apple iPad 3 rumors: thicker, sharper, coming soon
- PS Vita first edition bundle, game reviews
- Judge: Americans can be forced to decrypt
Latest CBS News Headlines
on Facebook Most Discussed Stories
on CBS News
- UK reaps bigger than expected January surplus
- Blur to play Hyde Park concert at end of Olympics
- Israel to rule on status of migrant children
- Pastor dies 5 months after Fla. church shooting
on Facebook Most Discussed Stories
on CBS News