October 21, 2008 12:18 AM
- Text
Delay String Ribbon Cutting Ceremony at Evergreen Solar
(MoneyWatch)
In order to reach sales of 200 MW in 2010, 620 MW in 2011 and 850 MW in 2012, Evergreen will need to expand its internal ribbon capacity by building a second string factory. The company believes it can begin construction of the next factory as late as June of 2009 and still meet 2010 capacity expansion targets. Given the current turmoil of the financial markets, however, Feld admitted: "obtaining funding for factory expansions at a cost of capital commensurate with the expected financial return of those expansions was really not available."
Given a cost structure in the $1.60 per watt range, management calculates the new 480 MW facility would require a total investment of about $800 million, of which the company expects to internally fund $400 million [which assumes the Devens facility is generating positive cash flow in 2009].
At September 27, the company owed about $449 million in long-tem contractual commitments and contingencies -- more than eight times nine-months 2009 aggregate product sales.
The Question: Is the financial survival on Evergreen Solar dependent on too many "ifs" -- such as capacity expansion tied to performance of capital markets?
The Company: Evergreen Solar, a manufacturer of String Ribbon solar power products.- The Filing: FORM 8-K filed with the SEC on October 16, 2008.
- The Finding: Evergreen Solar signed two new long-term sales contracts totaling more than 160 MW last week, extending the company's total contractual backlog to more than one-gigawatt (spanning over the next five years). The solar panels for these two contracts will be produced at the company's Devens, Massachusetts' facility. In order to meet manufacturing targets for 2010 - 2013, however, Evergreen will need to improve operating efficiencies, expand capacity at the Devens facility, and build a planned new factory -- which will require additional working capital.
In order to reach sales of 200 MW in 2010, 620 MW in 2011 and 850 MW in 2012, Evergreen will need to expand its internal ribbon capacity by building a second string factory. The company believes it can begin construction of the next factory as late as June of 2009 and still meet 2010 capacity expansion targets. Given the current turmoil of the financial markets, however, Feld admitted: "obtaining funding for factory expansions at a cost of capital commensurate with the expected financial return of those expansions was really not available."
Given a cost structure in the $1.60 per watt range, management calculates the new 480 MW facility would require a total investment of about $800 million, of which the company expects to internally fund $400 million [which assumes the Devens facility is generating positive cash flow in 2009].
At September 27, the company owed about $449 million in long-tem contractual commitments and contingencies -- more than eight times nine-months 2009 aggregate product sales.
The Question: Is the financial survival on Evergreen Solar dependent on too many "ifs" -- such as capacity expansion tied to performance of capital markets?
Latest Now in MoneyWatch
- Big banks, gov't officials strike $25B deal
- LinkedIn swings back to profit
- LinkedIn doubles revenue, beats growth estimates
- Kodak to stop making digital cameras, frames
- Market cap, schmarket cap, Apple still gets no respect
- Philip Morris Int'l income up nearly 8 percent
- Survey: Small biz plans big hires in 2012
- Freddie Mac: Mortgages inch higher but stay low
- Will the European debt crisis sink Obama's re-election?
- Banks in $25B deal to settle foreclosure abuses
- Joe Coffee: Scaling up without selling your soul
- Greek agreement accomplishes nothing
- 401K plans: New rules make costs clearer
- Are women leaders selling themselves short?
- Ask the Experts: New 401(k) rules
- Mortgage lenders strike a deal
- $25B foreclosure-abuse settlement reached
Latest CBS News Headlines
on Facebook
on CBS News
- Romney "glitter bomb" suspect loses his job
- APNewsBreak: Judge upholds Hyperion permit in SD
- NY Fashion Week: Wearable, sellable style for fall
- Summary Box: LinkedIn impresses with 4Q results
on Facebook
- Adele opens up about vocal cord surgery
- Tenn. father charged with murdering couple who"unfriended" daughter on Facebook
- Mo. teen gets life in prison for murder of 9-year-old girl
on CBS News