April 8, 2008 3:20 PM
- Text
Wave Power Still Not on the U.S. Horizon
(MoneyWatch)
Wave energy power hold promise as a new, renewable energy source. Nonetheless, moving beyond proof-of-concept in varied prototypes to full-scale commercial introduction is stilling running into roadblocks. The Aguçadora Wave Park, a commercial wave farm off the coast of Portugal, scheduled to be brought online in 2007, is but one of many examples where delays continue (for undisclosed reasons).
On December 18, 2007, Pacific Gas and Electric Company announced its support for plans to buy energy from the first commercial wave power plant, set 2.5 miles of the coast near Humboldt County, located in Northern California. The plan, to be designed and built by Canadian company, Finavera, will consist of eight floating "AquaBuOYs," with each generating electricity as it rises and falls with the waves.
The significance of this power purchase agreement -- when announced -- did not go unnoticed by clean energy advocates, for it was the first wave power project to win support from an electrical utility in the United States. The project is expected to begin delivering renewable, clean electricity in 2012, generating a maximum of 2 megawatts of electricity. Each megawatt can power about 750 homes.
Despite the fanfare, do not expect this wave farm to be plugged into the electric grid by 2012.
A key challenge remains in moving aqua-boy technology beyond proof-of-concept to commercial viability. In November 2007, Finavera's prototype AquaBuOY 2.0 sank off the Oregon coast, for reasons still yet to be disclosed. In addition, before Finavera can begin construction of the Humboldt wave farm, it and PG&E must spend the next two to three years vetting the permitting process, the overall project design, and detailed specifications to local, state, and federal regulators and community stakeholders, including fishermen, recreational boaters and environmental groups to understand the sitting, safety and environmental impacts of the wave energy plant. The licensing process will include all required environmental studies such as impacts on local fish habitat, marine mammal migration routes, and commercial and recreational fishing zones. Installation of the Humboldt wave farm will probably not even have begun by 2012.
Wave energy power hold promise as a new, renewable energy source. Nonetheless, moving beyond proof-of-concept in varied prototypes to full-scale commercial introduction is stilling running into roadblocks. The Aguçadora Wave Park, a commercial wave farm off the coast of Portugal, scheduled to be brought online in 2007, is but one of many examples where delays continue (for undisclosed reasons).On December 18, 2007, Pacific Gas and Electric Company announced its support for plans to buy energy from the first commercial wave power plant, set 2.5 miles of the coast near Humboldt County, located in Northern California. The plan, to be designed and built by Canadian company, Finavera, will consist of eight floating "AquaBuOYs," with each generating electricity as it rises and falls with the waves.
The significance of this power purchase agreement -- when announced -- did not go unnoticed by clean energy advocates, for it was the first wave power project to win support from an electrical utility in the United States. The project is expected to begin delivering renewable, clean electricity in 2012, generating a maximum of 2 megawatts of electricity. Each megawatt can power about 750 homes.
Despite the fanfare, do not expect this wave farm to be plugged into the electric grid by 2012.
A key challenge remains in moving aqua-boy technology beyond proof-of-concept to commercial viability. In November 2007, Finavera's prototype AquaBuOY 2.0 sank off the Oregon coast, for reasons still yet to be disclosed. In addition, before Finavera can begin construction of the Humboldt wave farm, it and PG&E must spend the next two to three years vetting the permitting process, the overall project design, and detailed specifications to local, state, and federal regulators and community stakeholders, including fishermen, recreational boaters and environmental groups to understand the sitting, safety and environmental impacts of the wave energy plant. The licensing process will include all required environmental studies such as impacts on local fish habitat, marine mammal migration routes, and commercial and recreational fishing zones. Installation of the Humboldt wave farm will probably not even have begun by 2012.
Latest Now in MoneyWatch
- Ohio unemployment hits 3-year-low
- Jill on Money: Retirement investing, allocation, long term care
- Could "web-lining" be dangerous?
- Insurers respond cautiously to contraceptive plan
- Judge: Legally, breastfeeding not related to pregnancy
- Budget deficit drops to $27 billion in January
- Why the Powerball Jackpot is part of my investment strategy
- Is the new VW Beetle diesel worth the money?
- Consumer sentiment highlights risks to recovery
- Valentine blues? 10 best cities to be single
- December trade deficit widens to $48.8 billion
- Alcatel-Lucent returns to profit in 2011
- 6 things never to say in a performance review
- $26B mortgage deal: Who gets the money?
- Friendly's CEO steps down
- Quarterly loss hits $3.3B at Postal Service
- Greeks rail against cuts as EU demands more
Latest CBS News Headlines
on Facebook
on CBS News
- Holliday leads 76ers past short-handed Cavs 99-84
- Nuggets upend Pacers 113-109
- Griffin, Paul lead Clippers over Bobcats 111-86
- Whitney Houston died in Beverly Hills hotel room
on Facebook
- Adele sings a cappella for Anderson Cooper
- Occupy protestors kicked out of CPAC
- CPAC: Will Sarah Palin spring a surprise?
- Beyonce and Jay-Z post first photos of Blue Ivy Carter
on CBS News